History of District 145 Facilities
School District 145 has a long history and tradition serving our communities. The following is an outline of the history of facility projects in our school district:
1918 Eagle-Union School District building erected
1921 Original three story building erected in Waverly
1958 Gymnasium, welding shop, library, 2 classrooms in Waverly
1963 Cafeteria, office, girl’s locker room, 9 classrooms in Waverly
1967 Shop annex, 4 classrooms (metal building) in Waverly
1968 6 classrooms and 3 offices added to Junior – Senior High
1969 Music area, wood shop, 2 classroom trailer added to Junior – Senior High
1970 Shop annex, 4 classrooms (metal building)
1971 Enclosed the high school courtyard, 2 classrooms, kindergarten annex
1974 Hamlow Elementary was constructed, 65,000 square feet; addition to Eagle Elementary, 26,200 square feet.
1975 Vocational Agriculture and Woods Annex (metal building)
1982 Bus Barn Facility and lot, Cost of $168,000
1983 10 classrooms, library, commons, reburbished the Junior High, added drama annex behind Junior High Auditorium, Total Cost of $994,125 (original bond was $1,300,000)
1992 District 145 Central Office was constructed
1996 Waverly High School, 126,000 square feet, Cost of $11,990,000
2000 Eagle Elementary classroom and gym addition and Hamlow Elementary kindergarten addition, cost of $5,285,000
2001 Original 1921 three story building demolished and 1 classroom added to Waverly Middle School, Cost of $449,000
2002 Waverly High School Irrigation well installation and tie in to under ground sprinkler system, Cost of $37,000
2003 Hamlow Elementary Classroom walls and doors added; fire sprinkler system added; Waverly Middle School roof replacement; window replacement; mapes panels under windows replaced; floor tile replaced, Total Cost of $2,030,000
2005 Waverly High School 28,000 square foot addition, full size double court additional gymnasium, 2 classrooms, 1 health / training classroom, restrooms, Cost of $3,300,000
2006 Waverly Middle School, 108,000 square feet, Cost of $13,480,000
2007 Waverly Intermediate School classroom renovations, office renovations, commons area renovation, carpet and cabinetry, Cost of $590,000
2010 Waverly High School install drain tile system around exterior of building and under gym floor; Eagle Elementary and Waverly Intermediate School interior fire doors and exterior entry doors, Hamlow Elementary School interior fire doors, Cost of $500,000
2012 Eagle Elementary School and Waverly Intermediate School HVAC improvements; Waverly High School, remediation of air quality issues and window replacement at Waverly High School, Cost of $1,500,000
2013 Hamlow Elementary School, installation of geothermal heating and cooling system, Cost of $3,342,000
2014 Waverly High School, removal of commons area skylight and replacement with rubber membrane roof
2014 Hamlow Elementary School, replacement of the Kal-Wall Panel skylight in the media center. Cost $184,400 (includes WHS skylight project).